Regional Rail Revival

The Regional Rail Revival is a joint initiative between the Australian federal government and the Victorian state government to upgrade all regional railway lines in Victoria. The project has an estimated total cost of A$4 billion.[1] A$2.3 billion of the project's total cost is being funded by the Australian Government.[2] It is being delivered by Rail Projects Victoria (RPV). The project is guided by the 2016 Regional Network Development Plan, which outlines the short, medium and long-term priorities for a modernised regional rail network.[3]

Regional Rail Revival
LocationVictoria, Australia
ProposerGovernment of Victoria
StatusUnder Construction
TypeRailway upgrade
Cost estimate$1.8 billion
Start dateOctober 2017
Completion dateLate 2021
StakeholdersGovernment of Australia (major funding partner)
Government of Victoria (minor funding partner)
V/Line (operator)

Projects

Regional Rail Revival is made up of multiple projects:[4]

  • Ararat Stabling
  • Ballarat Line Upgrade (completed early 2021)[5]
    • track duplication between Deer Park West and Melton (length of 18 kilometres (11 mi)), and at Bacchus Marsh
    • new Cobblebank station between Rockbank and Melton
    • reconstruction of Rockbank Station
    • upgrades to Bacchus Marsh, Ballan and Wendouree stations, including new platforms
    • new train stabling facility at Maddingley
    • passing loops at Ballan and Millbrook
    • signal and track upgrades
  • Bendigo and Echuca Line Upgrade[6]
    • modernised electronic train order (ETO) system from Bendigo to Swan Hill and Echuca
    • upgrades to ten level crossings between Eaglehawk and Bendigo with improved train detection technology
    • track upgrades on the Echuca Line, which will increase the maximum train speed on the line.
    • new stations at Huntly, Goornong, and Raywood. Goornong and Raywood stations were previously closed in 1979 and 1981 respectively.
    • potential reopening of Harcourt railway station (planning)
  • Donnybrook and Wallan station upgrades
  • Geelong Line Upgrade[7]
    • track duplication between South Geelong and Waurn Ponds
    • upgrades to South Geelong, Marshall and Waurn Ponds stations
    • new train maintenance and stabling facility at Waurn Ponds
    • level crossing removals
    • Armstrong Creek corridor extension (planning)
  • Gippsland Line Upgrade[8]
    • new rail bridge over the Avon River in Stratford (completed)
    • upgrades to Bunyip, Longwarry, Morwell and Traralgon stations, including new platforms
    • track duplication at Bunyip and Longwarry
    • extension of the Morwell crossing loop
    • level crossing and signalling upgrades
    • drainage structure upgrades
  • Murray Basin Rail Project
  • North-East Line Upgrade
    • introduction of VLocity trains on the line for the first time {completed December 2021}
  • Shepparton Line Upgrade
  • Warrnambool Line Upgrade (Stage 1)[9]
    • upgrades to 12 level crossings with improved train detection technology (completed)
    • signalling upgrades
    • new crossing loop at Boorcan
  • Warrnambool Line Upgrade (Stage 2)
    • upgrades to more than 50 level crossings with improved train detection technology
    • stabling upgrade at Warrnambool station
    • introduction of VLocity trains on the line for the first time

Construction

Timeline

New Avon River rail bridge in April 2021.

See also

References

  1. "Regional Rail Revival Package". Department of Infrastructure, Transport, Regional Development and Communications. Retrieved 3 February 2022.
  2. "Agreements on Inland Rail and Regional Rail Revival reached between Australian and Victorian governments". Urbanalyst. 19 March 2018. Retrieved 5 May 2020.
  3. "Regional Network Development Plan". Retrieved 5 May 2020.
  4. "Regional Rail Revival". Victoria's Big Build - Regional Rail Revivial. Retrieved 3 February 2022.
  5. "Ballarat Line Upgrade". Victoria's Big Build - Regional Rail Revivial. Retrieved 3 February 2022.
  6. "Bendigo and Echuca Line Upgrade". Victoria's Big Build - Regional Rail Revivial. Retrieved 3 February 2022.
  7. "Geelong Line Upgrade". Victoria's Big Build - Regional Rail Revivial. Retrieved 3 February 2022.
  8. "Gippsland Line Upgrade". Victoria's Big Build - Regional Rail Revivial. Retrieved 3 February 2022.
  9. "Warrnambool Line Upgrade". Victoria's Big Build - Regional Rail Revivial. Retrieved 3 February 2022.
  10. "Work Kicks Off On The Ballarat Line Upgrade". Retrieved 5 May 2020.
  11. "New Train Station For Melbourne's Growing West". Retrieved 5 May 2020.
  12. "Ballarat Line Upgrade Bringing Extra Benefits For Locals". Retrieved 20 May 2020.
  13. "Half A Billion Dollar Gippsland Line Upgrade Kicks Off". Retrieved 20 May 2020.
  14. "Ballan Station upgrade plans unveiled". Retrieved 20 May 2020.
  15. "Shepparton Station Stabling Construction Underway". Retrieved 20 May 2020.
  16. "Construction underway at Donnybrook and Wallan stations". Retrieved 20 May 2020.
  17. "Ballarat Line Upgrade to hit one million hours". Retrieved 20 May 2020.
  18. "New And Improved Rockbank Station". Retrieved 20 May 2020.
  19. "Construction underway on the new Avon River bridge". Retrieved 20 May 2020.
  20. "Victoria's Newest Station Opens At Cobblebank". Retrieved 20 May 2020.
  21. "Construction starts on Ararat stabling upgrade". Retrieved 20 May 2020.
  22. "Construction underway on Warrnambool Line level crossing upgrades". Retrieved 20 May 2020.
  23. "Donnybrook Station upgrade complete". Retrieved 20 May 2020.
  24. "Improved safety on the Warrnambool Line". Retrieved 20 May 2020.
  25. "Station Construction Fast-Tracked As Consultation Begins". Retrieved 7 August 2020.
  26. "Bendigo and Echuca Line Upgrade - Goornong Station". Victoria's Big Build - Regional Rail Revivial. Retrieved 3 February 2022.
  27. "Timetable changes on the Echuca and Swan Hill lines". Public Transport Victoria. Retrieved 16 July 2022.