Snowy 2.0 Pumped Storage Power Station

Snowy 2.0 Pumped Storage Power Station or Snowy Hydro 2.0 is a pumped-hydro battery megaproject in New South Wales, Australia. The dispatchable generation project connects two existing dams through a 27 kilometre underground tunnel and a new, underground pumped-hydro power station.[1] Construction began in 2019.[1] It is expected to supply two gigawatts of capacity and about 350,000 megawatt hours of large-scale storage to the national electricity market.[2][3]

Snowy 2.0 Pumped Storage Power Station
CountryAustralia
LocationSnowy Mountains
StatusUnder construction
Construction began2019
Owner(s)Snowy Hydro
External links
Websitehttps://www.snowyhydro.com.au/

It is designed for grid stabilization; to be a backup at times of peak demand and for when solar and wind energy are not providing power.[4] Snowy Hydro acts like a giant battery by absorbing, storing, and dispatching energy.[2] The battery is designed to operate for up to 175 hours of temporary supply.[5] It is Australia's largest renewable energy project.[6] The project is led by public company Snowy Hydro Limited.[6] When complete it is expected to have a severe impact on the price and reliability of electric power.[7]

History

Initial plans for a power station at the location were discussed in 1966.[8] Further studies were undertaken in 1980 and 1990.[8] The current project originated as the centrepiece of Malcolm Turnbull's climate change policy in 2017.[9] A feasibility study carried out in 2017 finding the project was both technically and financially feasible.[8] The study was released on 21 December 2017 and found the project cost would be between $3.8 and 4.5 billion.[10] The first tunnel that was completed by October 2022, was a 2.85 kilometre section that provided main access at Lobs Hole.[11] It was 10 metres in diameter and provides pedestrian and vehicle access into the power station.[11]

It was originally expected to be completed by 2024.[12] Snowy Hydro 2.0 has been beset by delays and cost blowouts.[9][4][3] Delays have been caused by the COVID-19 pandemic, global supply chain disruptions, complex design elements and variable site and geological conditions.[5] The delays have raised concerns that Snowy Hydro will not be ready in time for new solar and wind projects coming online as five coal-fired power stations close.[4] AEMO warns that supply gaps will emerge from 2025.[3] The project is currently expected to be fully operational by 2029.[9]

The project is using three tunnel boring machines to dig tunnels.[9] One of the machines was stuck for four months after encountering soft rock near Tantangara.[9][3]

Design and location

It is located remotely within the Mount Kosciuszko National Park in the Snowy Mountains.[2] Snowy Hydro 2.0 will use water from the Talbingo Reservoir (top storage) and Tantangara Reservoir (bottom storage).[7] The new power station will be located in a cavern 800 metres underground.[7] The underground location allows for reduced environmental impacts within the national park. The operational footprint of the facility is less than 0.01% of the total size of the park.[13]

The power station will measure 22 metres (m) wide, 50 m high and 250 m long.[6] The station will house six reversible Francis pump-turbine and motor-generator units.[12] Three units will be of variable speed with the remaining of synchronous speed. Each turbine will have a rated output of 333 megawatts.[14] Power generating equipment is being supplied by Voith.[14]

It will be connected to the grid via the HumeLink transmission line.[9]

See also

References

  1. "History". Snowy Hydro. Retrieved 5 May 2023.
  2. "The next generation of hydropower in Australia". SMEC. Retrieved 5 May 2023.
  3. Morton, Adam; Rose, Tamsin; Hannam, Peter (3 May 2023). "Snowy Hydro 2.0 project hit by delay of up to two years and another cost blowout". The Guardian. Retrieved 5 May 2023.
  4. Toscano, Nick; Foley, Mike (3 May 2023). "Snowy 2.0 pumped hydro project hit with new delays, cost blowouts". The Sydney Morning Herald. Retrieved 5 May 2023.
  5. "Timeline, budget reset for Snowy 2.0 pumped storage". Hydro Review. 5 April 2023. Retrieved 5 May 2023.
  6. "Snowy 2.0: A pumped-storage plant of colossal proportions". Tractebel. 20 July 2022. Retrieved 5 May 2023.
  7. Ziffer, Daniel (6 January 2023). "Snowy Hydro could change our electricity grid and bring cheap power. But we have to build it". ABC News. Australian Broadcasting Corporation. Retrieved 5 May 2023.
  8. Cella, Lauren (24 January 2020). "Snowy 2.0 underway". Pump Industry. Retrieved 5 May 2023.
  9. Dhanji, Krishani (3 May 2023). "Snowy Hydro 2.0 pumped-hydro battery project faces a further two years of delays". ABC News. Australian Broadcasting Corporation. Retrieved 5 May 2023.
  10. "Snowy 2.0 feasibility study released". ARENA. Retrieved 5 May 2023.
  11. "Milestone first tunnel completed for Snowy 2.0". Snowy Hydro. 11 October 2022. Retrieved 5 May 2023.
  12. "Snowy 2.0 Hydropower Project, New South Wales". PowerTechnology. Verdict Media. Retrieved 5 May 2023.
  13. "FAQs". Snowy Hydro. Retrieved 5 May 2023.
  14. "Voith Snowy 2.0". ICN Gateway. Retrieved 5 May 2023.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.