Line 5 (Mumbai Metro)

Orange Line 5 of the Mumbai Metro, or the Thane-Bhiwandi-Kalyan Line, is part of the metro system for the city of Mumbai, India. This line construction is divided into two phases.[1] Phase 1 will cover the metro route from Thane to Bhiwandi, and Phase 2 will cover the other stretch from Bhiwandi to Kalyan. In a recent update in March 2022, MMRDA has come up with a new plan to build a 3 km (1.9 mi) underground track to prevent the demolition of thousands of structures. The new plan for phase 2 will also increase the project's overall cost by ₹1,727 Cr.[2]

Mumbai Metro Orange Line 5
Overview
StatusUnder Construction
OwnerMumbai Metropolitan Region Development Authority (MMRDA)
LocaleThane, Mumbai, Maharashtra, India
TerminiThane
Stations17
WebsiteLine 5
Service
TypeMetro
SystemMumbai Metro
Depot(s)Kasheli
History
Commenced18 October 2019 (2019-10-18)
Planned opening2025 (2025)
Technical
Line length24.9 km (15.5 mi)
CharacterElevated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Route map

Line 5
to Line 12
Right arrow towards CSMT
Kalyan APMC Depot
0.0000
Kalyan APMC
0.7000
Kalyan Railway Station on Central line
Left arrow towards Khopoli and Down arrow towards Kasara
1.4640
Sahajanand Chowk
2.0980
Durgadi Fort
Ulhas River
3.8940
Kongaon
Kongaon MIDC Depot
6.1950
Govegaon MIDC
7.1980
Rajnouli Village
8.9840
Temghar
10.7640
Gopal Nagar
11.4850
Bhiwandi
12.4020
Dhamankar Naka
14.2420
Anjur Phata
Vasai Road–Roha line
15.7190
Purna
17.7960
Kalher
19.2370
Kasheli
Vasai Creek
22.9100
Balkum Naka
23.7860
Kapurbawdi (Thane)
on Line 4

The 24.9 km (15.5 mi)-long Thane-Bhiwandi-Kalyan Metro-V corridor will have 17 stations and will cost Rs. 8,416 crores. It will be totally an elevated corridor for Phase 1 however, Phase 2 is still under planning phase. It will connect Thane to Bhiwandi and Kalyan in the eastern suburbs. The stations include Kapurbawdi in Thane (West), Balkum Naka, Kasheli, Kalher, Purna, Anjur Phata, Dhamankar Naka, Bhiwandi, Gopal Nagar, Temghar, Rajnouli Village, Govegaon MIDC, Kongaon, Durgadi Fort, Sahajanand Chowk, Kalyan Railway Station. MMRDA approved the line on 19 October 2016 and Maharashtra Cabinet on 24 October 2017.[3]

After the approval of Metro line 5, CM Devendra Fadnavis had a meeting with MP Shrikant Shinde, who suggested to extend the Thane-Bhiwandi-Kalyan metro corridor to far-eastern suburbs like Dombivli, Badlapur, and Ambernath, and link it with the Navi Mumbai lines. The population in Dombivli, Badlapur, Ambernath, and Diva is growing rapidly because many middle-class populations started moving here in search of affordable budget homes. CM Devendra Fadnavis directed MMRDA to prepare a detailed project report (DPR) for Taloja – Dombivli – Kalyan metro corridor. On 21 November 2018, CM Devendra Fadnavis approved the detailed project report (DPR) for Mumbai Metro Line 12 (Kalyan-Dombivli-Taloja), an extension of the Metro line 5 metro corridor.[4]

The MMRDA began carrying out survey work for the line by December 2017.[5] Survey work was interrupted due to protests by some shopkeepers and residents of Bhiwandi.[6]

The plan is revised for phase 2 construction

Construction

Phase 1 – Thane to Bhiwandi

Sr. No.Name of Work Description Status for year 2021[7]
1 May 2021 2 Aug 2021
1Soil Investigation Works Soil Investigation Work For Pier Foundation Completed 94% 95.15%
2Utility Works Works Completed 80% 84.44%
3Piling Works Piling Work For complete

Foundations Completed

73% 77.57%
4Pile Cap Works Pile Cap Work Completed 67% 71%
5Open Foundation Works Foundation Works 70% 76.15%
6Pier Works Piers Cast 60% 59.64%
7Pier Cap Works Pier Caps Work Completed 23% 43.33%
8Girder Erection Girder Erected 12% 14.89%
9U Girder works are in progress 7% 20.09%
10U Girder works are in progress 11% 26.20%
11I Girder works are in progress 3% 1.88%

Phase 2 – Bhiwandi to Kalyan

Delhi Metro Rail Corporation is appointed to finalize the alignment and to prepare the revise DPR

Stations

There will be 17 stations on Line 5.

Orange Line 5
# Station Name Status Connections Layout
EnglishMarathi
1KapurbawdiकापूरबावडीUnder ConstructionGreen Line 4 (Under Construction)Elevated
2Balkum Nakaबाळकुम नाकाUnder ConstructionNoneElevated
3KasheliकशेळीUnder ConstructionNoneElevated
4Kalherकाल्हेरUnder ConstructionNoneElevated
5Purnaपूर्णाUnder ConstructionNoneElevated
6Anjur Phataअंजूर फाटाUnder ConstructionIndian RailwaysElevated
7Dhamankar Nakaधामणकर नाकाUnder ConstructionNoneElevated
8BhiwandiभिवंडीUnder ConstructionNoneElevated
9Gopal Nagarगोपाल नगरUnder ConstructionNoneElevated
10TemgharटेमघरUnder ConstructionNoneElevated
11Rajnouli Villageराजनौली गावUnder ConstructionNoneElevated
12Govegaon MIDCगोवेगाव एमआयडीसीUnder ConstructionNoneElevated
13KongaonकोणगावUnder ConstructionNoneElevated
14Durgadi Fortदुर्गाडी किल्लाUnder ConstructionNoneElevated
15Sahajanand Chowkसहजानंद चौकUnder ConstructionNoneElevated
16Kalyan Railway Stationकल्याण रेल्वे स्थानकUnder ConstructionCentral line, Indian RailwaysElevated
17Kalyan APMCकल्याण एपीएमसीUnder ConstructionOrange Line 12 (Proposed)Elevated

References

  1. "Mumbai Metro - Line 5 (Orange Line)". Mumbai Metro Times - Your Metro Guide. Retrieved 22 March 2022.
  2. "3km stretch on Bhiwandi - Kalyan Metro line to be built underground, saving 735 structures". Hindustan Times. 18 March 2022. Retrieved 22 March 2022.
  3. "Mumbai Metro's corridor 5 and 6 gets Maharashtra cabinet approval". Livemint. 24 October 2017. Retrieved 9 October 2018.
  4. "Mumbai Metro - Line 5 (Orange Line)". Mumbai Metro Times - Your Metro Guide. Retrieved 22 March 2022.
  5. "Mumbai Metro-5 to move through crowded areas of Thane". The Asian Age. 28 December 2017. Retrieved 9 October 2018.
  6. "Bhiwandi residents oppose Metro 5". The Asian Age. 1 August 2018. Retrieved 9 October 2018.
  7. "Mumbai Metropolitan Region Development Authority - Metro Line - 5".


This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.