E5 expressway (Philippines)
Expressway 5 (E5) forms part of the Philippine expressway network.[1] Collectively known as the North Luzon Expressway Harbor Link Project (NLEX Harbor Link Project),[2] it runs from Congressional Avenue and Luzon Avenue, both components of Circumferential Road 5, in Quezon City to Radial Road 10 in Navotas, linking the North Luzon Expressway to the Port of Manila. Currently, its segment from Mindanao Avenue in Valenzuela to Navotas is operational.
![]() | ||||
---|---|---|---|---|
NLEX Harbor Link | ||||
Route information | ||||
Maintained by NLEX Corporation | ||||
Length | 24.85 km (15.44 mi) Segment 8.1 (Mindanao Avenue Link) – 2.7 km (1.7 mi) Segment 9 (Karuhatan Link) – 2.4 km (1.5 mi) Segment 10 (Harbor Link) – 8.25 km (5.13 mi) (including C-3–R-10 section) Segment 8.2 (C-5 Link) – 11.5 km (7.1 mi) (construction pending) | |||
Major junctions | ||||
West end | ![]() | |||
| ||||
East end | ![]() Future: ![]() | |||
Location | ||||
Country | Philippines | |||
Major cities | Caloocan, Malabon, Navotas, Quezon City, Valenzuela | |||
Highway system | ||||
| ||||
|
History

Construction of NLEX Segment 8.1 (Mindanao Avenue Link), the first segment of the Harbor Link project, broke ground on April 2, 2009,[3] with actual construction work beginning on April 21, 2009.[4] It was then opened on June 5, 2010.[5] The spur road became part of the C-5 Road North Extension and is built to provide another entry point to the expressway from Metro Manila and decongest Balintawak Interchange.[6]
In 2013–2014, the construction of NLEX Segments 9 (Karuhatan Link) and 10 (Harbor Link) broke ground.[7][8] On March 18, 2015, NLEX Segment 9 was opened, providing continuation to Segment 8.1 that runs from the western side of the Smart Connect Interchange to MacArthur Highway in Karuhatan, Valenzuela.
On February 28, 2019, the main stretch of NLEX Segment 10 from MacArthur Highway to C-3 Road in Caloocan was inaugurated and opened to traffic.[9][10] However, this section of NLEX Segment 10 was supposed to be operational in December 2016,[11] but was delayed repeatedly due to right of way issues and delayed ROW acquisition. On February 21, 2020, its C-3–R-10 section was partially opened up to its Malabon (Dagat-Dagatan) exit ramp.[12] On June 15, its remaining section up to Radial Road 10 was finally opened.[13] This section was originally expected to open in March 2020, but was delayed due to the COVID-19 pandemic.
Route description
The NLEX Harbor Link Project is the extension of the North Luzon Expressway that runs currently from Mindanao Avenue in Valenzuela at the east to Radial Road 10 in Navotas at the west, where an access to the Port of Manila is found. It aims to connect with Port of Manila, while improving cargo movement between NLEX and Radial Road 10. It is divided into four segments, namely: Segment 8.1 (Mindanao Avenue Link), 8.2 (C-5 Link / Citi Link), 9 (Karuhatan Link), and 10 (Harbor Link).[2] It forms part of the expressway's open section. Both Segments 8.1 and 9 are components of Circumferential Road 5 (C-5) of Manila's arterial road network.
Mindanao Avenue to NLEX main

NLEX Segment 8.1 (Mindanao Avenue Link) is a four-lane, 2.7-kilometer (1.7 mi) expressway that runs from the Smart Connect Interchange to Mindanao Avenue in Valenzuela. Lying on the ground level east of the interchange, it begins at the intersection with Mindanao Avenue in Barangay Ugong and then approaches the Mindanao toll plazas, widening to 6 lanes serving only westbound traffics. It terminates at the Smart Connect Interchange with NLEX Main and continues to the west as Segment 9 (Karuhatan Link).
NLEX main to Karuhatan

NLEX Segment 9 (Karuhatan Link) is a four-lane, 2.4-kilometer (1.5 mi) expressway that runs from Smart Connect Interchange to MacArthur Highway in Karuhatan, Valenzuela. It is the first segment of the NLEX Harbor Link project.[14] It begins at the Smart Connect Interchange with NLEX Main, picking-up from where Segment 8.1 (Mindanao Avenue Link) left off. Lying on the ground level west of the interchange, it then traverses Barangays Gen. T. De Leon, Parada, and Maysan, where two exits towards the first two barangays, respectively, are found. It then enters Barangay Karuhatan, where it approaches the Karuhatan toll plaza, widening to 6 lanes serving only eastbound vehicles, and Segment 10 (Harbor Link) and finally terminates at MacArthur Highway.
Karuhatan to Navotas

_area(2022)-3jwilz.jpg.webp)
NLEX Segment 10 (Harbor Link), the second phase of the NLEX Harbor Link project, is a four-lane, 5.65-kilometer (3.51 mi) fully elevated expressway which connects with the Karuhatan Link (Segment 9) in Valenzuela to C-3 Road in Caloocan, where two ramps carry it to the west for another 2.6 kilometers (1.6 mi) up to Radial Road 10 (R-10) in Navotas.[14] It begins at Karuhatan Exit with Segment 9 (Karuhatan Link) and MacArthur Highway. The section near the northern terminus traverses an industrial and residential area, which necessitated the demolition of numerous houses, buildings, and warehouses. It soon follows the railway right-of-way where it rises up to as high as 19 meters (62 ft) to provide necessary ground clearance for the viaduct carrying the future Manila–Clark Railway of the Philippine National Railways (PNR). It then crosses Tullahan River, where it enters Malabon. It then enters Caloocan, where past Samson Road and the PNR rolling stock shops in Caloocan, it shifts east of the railway's right of way, which also necessitated the demolition of a wet market. An exit to C-3 Road could then be found before meeting the Caloocan Interchange, where the expressway veers west as the C3–R10 spur alignment with connection to the under-construction NLEX Connector (NLEX-SLEX Connector Road) that would lead southwards to Manila. The 2.6-kilometer (1.6 mi) C3–R10 section runs above C-3 Road, where a westbound exit ramp towards Dagat-Dagatan Avenue could be found. It then crosses the Navotas River and enters Navotas, where it veers southeast towards R-10 and ends at the Navotas Interchange, which provides access to the Port of Manila via Mel Lopez Boulevard.
At the Navotas Interchange, the expressway has a possible future connection to the proposed NLEX–CAVITEX Port Expressway Link or Harbor Link Port Access Mobility Facility towards Manila–Cavite Expressway (CAVITEX) or Anda Circle, respectively.[15][16]
Future
Segment 8.2 (NLEX–C-5 Link)
NLEX Segment 8.2, also named NLEX C-5 Link and NLEX Citi Link,[14][17] will be an 11.5-kilometer (7.1 mi) segment part of the NLEX Harbor Link Project that will connect the existing NLEX Segment 8.1 (Mindanao Avenue Link) to Katipunan Avenue, a part of C-5. It is divided into two sections: the 8.30-kilometer (5.16 mi) Section 1 from Mindanao Avenue to Luzon Avenue and the 3.2-kilometer (2.0 mi) Section 2 from Luzon Avenue to C.P. Garcia Avenue.[2][18][19] The planned segment will at first run parallel to Republic Avenue before making a southward turn to Luzon Avenue after which it will then cross to Commonwealth Avenue and end at the intersection of C.P. Garcia and Katipunan Avenues.[14] The segment will include five interchanges at Mindanao Avenue, Quirino Highway, Regalado Avenue, Congressional and Luzon Avenues, and Katipunan and C.P. Garcia Avenues, with three local road crossings at Sauyo Road, Chestnut Avenue, and Commonwealth Avenue.[20][21]
The project implementation has been delayed for years due to right of way issues,[22][23] as it will affect informal settlers in 8 barangays of Quezon City.[24] Construction of the expressway segment's 2-kilometer (1.2 mi) Section 1A between Mindanao Avenue and Quirino Highway is set to commence in September 2021.[25]
Exits



Exit numbers are numbered by kilometer posts. The kilometer count, which would be shown here in its approximate values, increments east and west of Smart Connect Interchange as it branches off NLEX Main, with Rizal Park in Manila designated as kilometer 0.
Province | City/Municipality | km | mi | Exit | Name | Destinations | Notes |
---|---|---|---|---|---|---|---|
Quezon City | C.P. Garcia | ![]() | Future eastern end of expressway;[18] possible link to the proposed C-5 Expressway | ||||
Congressional | ![]() | ||||||
Regalado[26] | Regalado Avenue | ||||||
Quirino Highway | ![]() | ||||||
Valenzuela | 15.9 | 9.9 | Mindanao Avenue | ![]() | Current eastern terminus; current eastern end of C-5 concurrency | ||
15.39 | 9.56 | Mindanao toll plaza (westbound only) | |||||
15.29 | 9.50 | Mindanao toll plaza expansion (westbound only; exclusively for Class 1) | |||||
13 | 8.1 | Smart Connect Interchange | ![]() | Cloverleaf interchange with collector lanes | |||
14.71 | 9.14 | Parada | Parada, Maysan | Westbound exit only | |||
15.00 | 9.32 | Gen. T. De Leon | Gen. T. de Leon | Eastbound exit only | |||
16.15 | 10.04 | Karuhatan toll plaza (eastbound only) | |||||
16.2– 17.5 | 10.1– 10.9 | Karuhatan | ![]() | Diamond interchange; western end of C-5 concurrency; Former western terminus (2015-2020) | |||
Malabon | No major junctions | ||||||
Caloocan | C-3 Road | ![]() | Southbound exit and northbound entrance | ||||
Caloocan Interchange | NLEX Connector | Directional T interchange; veers west to C3–R10 section | |||||
Malabon (Dagat-Dagatan) | Dagat-Dagatan Avenue – Caloocan, Malabon | Westbound exit and future eastbound entrance[27] | |||||
Navotas | ![]() | Future westbound exit and eastbound entrance[28] | |||||
Navotas Interchange (C-3–R-10 Ramp)[28] | ![]() | Western terminus, future connection to Southern Access Link Expressway, NLEX–CAVITEX Port Expressway Link or Harbor Link Port Access Mobility Facility | |||||
1.000 mi = 1.609 km; 1.000 km = 0.621 mi
|
References
- "2015 DPWH Road Data". Department of Public Works and Highways. Retrieved March 5, 2018.
- "NLEX HARBOR LINK PROJECT (Segments 8.1, 8.2, 9 & 10)". Department of Public Works and Highways. Retrieved July 17, 2021.
- "MNTC starts construction of roads connecting NLEX from all directions". GMA News and Public Affairs. April 2, 2009. Retrieved July 8, 2016.
- "NLEX's Segment 8.1 opens today, June 5" (Press release). Manila North Tollways Corporation. June 5, 2010. Archived from the original on June 20, 2010. Retrieved July 8, 2016.
- "PGMA inaugurates P2.1-B NLEX-Mindanao Avenue Link". Philippines News Agency. June 5, 2010. Archived from the original on November 19, 2011. Retrieved July 8, 2016.
- Reyes, Mary Ann L.L. (July 12, 2015). "Seamless travel". The Philippine Star. PhilStar Daily, Inc. Retrieved July 8, 2016.
- Mangunay, Kristine Felisse; Montecillo, Paolo G. (February 13, 2013). "NLEx Harbor Link expressway breaks ground; new road seen to ease Metro traffic". Philippine Daily Inquirer.
- "NLEX concessionaire breaks ground for Harbor Link Segment 10". TopGear Philippines. March 4, 2014.
- "Duterte leads inauguration of NLEX Harbor Link Segment 10, groundbreaking of NLEX Connector". NLEX Corporation. February 28, 2019. Retrieved May 11, 2021.
- Laurel, Drei (March 1, 2019). "NLEX Harbor Link Segment 10 is finally open". Top Gear Philippines. Retrieved May 11, 2021.
- Manabat, Jacque (July 21, 2015). "MNTC eyes completing NLEX-Harbor Link by Dec 2016". ABS-CBN News. Retrieved May 11, 2021.
- Rey, Aika (February 22, 2020). "NLEX Harbor Link Malabon Exit open to motorists". Rappler. Retrieved May 22, 2020.
- "NLEX opens latest Harbor Link section". CNN Philippines. June 15, 2020. Retrieved June 15, 2020.
- "Concessions". NLEX Corporation. Retrieved May 22, 2020.
- Mercurio, Richmond (March 2, 2020). "NLEX keen on Port Expressway Link project". The Philippine Star. Retrieved May 18, 2020.
- Mercurio, Richmond (February 14, 2020). "Construction to start soon on Harbor Link extension". The Philippine Star. Retrieved May 18, 2020.
- "FIRST QUARTER 2021 FINANCIAL AND OPERATIONAL RESULTS ANALYSTS' BRIEFING" (PDF). Metro Pacific Investments Corporation. May 5, 2021. Retrieved June 27, 2021.
- "Environmental Impact Statement (EIS) Summary for the Public in English NLEX-C5 (Segment 8.2) North Link Project" (PDF). Environmental Impact Assessment and Management Division. March 2021. Retrieved July 17, 2021.
- "Road and Bridge Inventory". www.dpwh.gov.ph. Retrieved June 14, 2020.
- "MNTC | Projects". Manila North Tollways Corporation. Archived from the original on September 14, 2018. Retrieved September 14, 2018.
- "Silip sa Sauyo at Proyektong NLEX 8.2". Manila Today (in Filipino). September 4, 2018. Retrieved September 27, 2020.
- "Right of way issue delays NLEX segment". The Manila Times. June 8, 2015. Retrieved July 18, 2021.
- Balinbin, Arjay L. (February 19, 2020). "DPWH readies NLEx 'Segment 8.2'". BusinessWorld. Retrieved July 18, 2021.
- Tuquero, Loreben (November 12, 2019). "House panel wants in-city relocation for 18k informal settlers along QC's Segment 8.2". Rappler. Retrieved July 18, 2021.
- Balinbin, Arjay L. (July 19, 2021). "NLEX targets to start P2-B QC extension by early Sept". BusinessWorld. Retrieved July 19, 2021.
- "NLEX-C5 (Segment 8.2) North Link Project" (PDF). Environmental Impact Assessment and Management Division. August 2019. Retrieved September 27, 2020.
- "NLEX Harbor Link C3-R10 Section Progress Video (as of June 1, 2020)". YouTube. June 1, 2020.
- Patinio, Ferdinand (June 15, 2020). "NLEX Harbor Link C3-R10 section now open to motorists". Philippine News Agency.